Get premium membership and access revision papers, questions with answers as well as video lessons.

Project Management Question Paper

Project Management 

Course:Bachelor Of Science In Entrepreneurship Studies

Institution: Moi University question papers

Exam Year:2010



UNIVERSITY EXAMINATIONS: 2009/2010
SECOND YEAR EXAMINATION
PROJECT MANAGEMENT
DATE: APRIL 2010 TIME: 2 HOURS
INSTRUCTIONS: Answer Question ONE and Any other TWO Questions
QUESTION ONE
A project has the following activities, precedence relationships and activity duration.
Activity Precedence Duration in hours
A None 100
B None 140
C A & B 1800
D B 300
E B, C & D 300
F E 70
G F 50
H G 70
a. (i) Draw a Gantt chart for the project (6 Marks)
(ii) Identify the activities comprising the critical path (2Marks)
(iii) Draw a network diagram for the project showing EF, ES, and D for each. (12 Marks)
b. Discuss the importance of managing a project (10Marks)
QUESTION TWO
a) Enumerate the main responsibilities of a project support office. (4 Marks)
b) Discuss the FOUR major differences between a project manager and a functional manager.
(16 Marks)
QUESTION THREE
a) State and explain the impact due to leadership emphasis in project environment. (12Marks)
b) (b) What is the importance of teams as one of the project success factors? (8Marks)
QUESTION FOUR
Write short notes on ANY TWO of the following concepts in project management
a) Configuration management (10 Marks)
b) Risk identification and control (10 Marks)
c)Project plan (10 Marks)
QUESTION FIVE
a) Outline the important stages which make up the project life cycle (10 Marks)
b) Discuss the critical success factors for a project (10 Marks)






More Question Papers


Popular Exams


Mid Term Exams

End Term 1 Exams

End Term 3 Exams

Opener Exams

Full Set Exams



Return to Question Papers