Dbit 206: It Project Management Question Paper
Dbit 206: It Project Management
Course:Diploma In Business Information Technology
Institution: Kenya Methodist University question papers
Exam Year:2010
FACULTY : SCIENCE AND TECHNOLOY
DEPARTMENT : CIS AND BIT
TIME : 2 HOURS
INSTRUCTIONS Answer Question ONE and any Other TWO Questions
Question 1
a) How do IT project management differ from managing other projects such as construction projects.(4marks)
b) Explain four types of resources a project manager must learn to master to ensure successful projects. (4marks)
c) Describe three types of skills a seasoned project manager should possess. (3marks)
d) Discuss the role of five IT project management tools used in modern projects (5marks)
e) Project scheduling involves integrating tasks and resources within a framework of time. Describe two approaches to scheduling. (4marks)
f) What is a project scope?Explain ways in which a project scope can be managed. (5marks)
g) State any three types of projects. (3marks)
h) What software would you recommend to project managers and why? (2marks)
Question 2
a) Make brief notes about project monitoring and control. Why is project monitoring and control important to IT project managers? (8marks)
b) How is project management different from operational management? (12marks)
Question 3
a) To plan and see an IT project successful often involves a series of steps.State and explain the steps involved. (12marks)
b) Discuss the areas you would recommend IT projects to watch out to avoid project failures. (8marks)
Question 4
a) Consider the following project tasks from a renown IT consultancy:The tasks are not necessarily in a sequential order.Each task has an approximate 2days period.
i) Secure project sponsorship
ii) Secure core resources
iii) Conduct needs analysis
iv) Develop preliminary budget
v) Incorporate feedback on software specifications
vi) Secure required resources
vii) Develop functional specifications
viii) Obtain approval to proceed
ix) Develop code
x) Unit Testing
xi) Modify code
xii) Training
xiii) Documentation
xiv) Install/deploy software
xv) Develop user manuals
xvi) Train support staff
Develop a fishbone diagram to illustrate the plan you would recommend to this company for program execution. (10marks)
b) Create a Gantt Chart to indicate the task execution schedule given each task has a finish-to-start dependency with its successor task apart from iv.xi and xiii. (10marks)