KENYATTA UNIVERSITY
UNIVERSITY EXAMINATIONS 2009/2010
SUPPLEMENTARY EXAMINATION FOR THE DEGREE OF MASTER OF
BUSINESS ADMINISTRATION
BMS 606:
PROJECT MONITORING AND EVALUATION

DATE: Friday, 1st October, 2010

TIME: 9.00 a.m. – 12.00 p.m.
------------------------------------------------------------------------------------------------------------
INSTRUCTIONS:
Attempt ALL questions.
Question One
“A community incapable of evaluating its own undertakings is a community that cannot manage the project itself”. Discuss. (20 marks)

Question Two
Critically evaluate the role played by Evaluation Standards and Guidelines citing the various categories that exist. (20 marks)

Question Three
Every intervention deliberately undertaken by a project organization should, of necessity, have an elaborate evaluation plan ideally created during the design phase of the project. Explain the significance of this tool by clearly discussing its components. (20 marks)

Question Four
An increasingly popular technique in project monitoring and evaluation is the Participatory Monitoring and Evaluation approach. Discuss the significance of effective stakeholder analysis in the success of this approach. (20 marks)

Question Five
Provide a comprehensive analysis of the differences between formative and summative evaluation and outline the merits and demerits of each approach. (20 marks)