Bbit 315:Project Management 1St Trimester 2014 Question Paper

Bbit 315:Project Management 1St Trimester 2014 

Course:Bachelor Of Business Information Technology

Institution: Kenya Methodist University question papers

Exam Year:2014



IT PROJECT MANAGMENT (CISY 404) (DBIT 222) (DCIS 203) (BBIT 315) 1ST TRIMESTER 2014
KENYA METHODIST UNIVERSITY

END OF 1'ST 'TRIMESTER 2014 (EVENING) EXAMINATION

FACULTY : COMPUTING & INFORMATICS
DEPARTMENT : COMPUTER SCIENCE AND BUSINESS
INFORMATION
UNIT CODE : CISY 404/DBIT 222/DCIS 203/BBIT 315
UNIT TITLE : IT PROJECT MANAGEMENT
TIME : 2 HOURS


Instructions: Answer question one and any other two questions.

Question One

Explain how the success of a project can be assessed.
(5mks)
How can a project be brought back on schedule, if it is found to be running late.
(5mks)
Describe briefly the two technique that can be used to identify the cost of a project.
(4mks)
Draw and label the structure of a standard project.
(4mks)
With examples, distinguish between quality assurance and quality control.
(4mks)
Describe six items that should be included in a regular progress report to the project sponsor.
(6mks)
Question Two

You are approaching the end of the second stage of a four stage project. You have created a plan to show the work that needs to be done and you must assign resources to the task. (5mks)
Describe the factors that you would consider when allocating staff to a task.
(5mks)
Explain the actions that you could take incase you don’t have enough skillful people to finish the project on time.
(8mks)
What steps would you follow to have a new resource person.
(7mks)
Question Three

Explain the major elements of a configuration management. (6mks)
What are the differences between the Gantt chart and the network diagram?
Highlight the advantages and the disadvantages of the Gantt chart and the network diagram.
(10mks)
Question Four

Explain five characteristics set by ISO9126 to measure the quality of software.
(10mks)
What quality control activities can be used to remove quality defects in a software project?
(5mks)
Explain five methods of managing a project risk.
(5mks)