KENYATTA UNIVERSITY
UNIVERSITY EXAMINATIONS 2008/2009
FIRST SEMESTER EXAMINATION FOR THE DEGREE OF MASTERS IN
ENVIRONMENTAL PLANNING AND MANAGEMENT
EPM 651: PROJECT DEVELOPMENT PLANNING AND MANAGEMENT


DATE: Tuesday 2nd December, 2008

TIME: 9.00 a.m. – 12.00 noon

INSTRUCTIONS
Answer question ONE (1) and any other TWO (2).

1.
Define the following terminologies and indicate their usefulness in the practice of
project development planning and management in Kenya:

(i)
Project inputs




[5 marks]

(ii)
Strategic plans




[5 marks]

(iii)
Project cycle management (PCM)


[5 marks]

(iv)
Resource planning




[5 marks]

(v)
Performance contracting



[5 marks]

(vi)
Constituency Development Fund (CDF)

[5 marks]

2.
Explain the reasons for the increasing interest in Project Development Planning
and Management over the last five decades.

[20 marks]

3.
Citing examples, discuss the procedural steps in the project development planning
and management process.




[20 marks]

4.
Discuss the effects of Environmental Impact Assessment (EIA) on projects
development planning and Management in Kenya.
[20 marks]


2

5.
You have served as a Chief Executive Officer (CEO) of Rerurb Project
Development and Management Consultants. From your study and practice of
managerial function of controlling, certain principles (truths) have been implied
and observed. These truths may be similar to truths in other areas of
Environmental management and the nature and purpose of control. State and
discuss these principles.





[20 marks]

……………