FIRST SEMESTER EXAMINATION FOR THE DEGREE OF BACHELOR OF ENGINEERING
SET 401: PROJECT MANAGEMENT
DATE: Tuesday 25th November 2008 TIME: 2.00pm-4.00pm
------------------------------------------------------------------------------------------------------------
INSTRUCTIONS:
Question One is compulsory. Answer any other two questions
(Table of normal areas attached)
Question One ( 30 marks)
a) Differentiate between planning and scheduling in project management. (2marks)
b) Highlight the six steps involved in critical path network development. (3marks)
c) Define the terms as used in project scheduling.
i) Critical path
ii) An activity
iii) Earliest finish time (EFT)
v) Total float (TF) (5marks)
2
d) Construct an AON network board on the following information
Activity immediate predecessors
A -
B -
C -
D A,B
E C (3marks)
e) Describe the steps involved in formulation a linear programming model. (5marks)
f) Given the following network, determine the Easiest and Latest activity times and compute the critical path.
(12marks)
Question Two (20marks)
a) Differentiate between project planning and project management. (2marks)
b) The primary challenge of project management is to achieve all the goals and objectives while adhering to the classic project constraints(“traditional triple constraints”) Highlight these constraints. (3marks)
c) Discuss briefly giving examples the main five (5) processes within the project cycle. (15marks)
3
Question Three (20marks)
a) Define the following terms that are commonly used in financial and economic appraisal of the project.
i) Payback period
ii) Average rate of return
iii) Net present value (NPV)
iv) Profitability index. (8marks)
b) The BIZ training company limited is considering buying a new online system to enable them to deliver the training they do for their corporate clients. Each system has a range of functionality but they differ quite a bit in what they offer. Both systems would do the job that BIZ training are looking for . The required rate of return for both systems is 12%. The expected annual after tax cash inflows from each system are as follows.
YEAR
SYSTEM A
(Kshs)
SYSTEM B
(Kshs)
0
-60,000
-60,000
1
12,000
13,000
2
12,000
13,000
3
12,000
13,000
4
12,000
13,000
5
12,000
13,000
6
12,000
13,000
i) Calculate the net present value (NPV), profitability index (PI) and internal rate of return (IRR). (11marks)
ii) Indicate if the system should be accepted. (1marks)
4
Question Four (20marks)
a) To complete a housing project, James has laid out the seven major activities involved. Those activities have been labeled A through G in the following table which also shows the estimated completion times in weeks and immediate predecessors.
Activity a m b immediate
predecessors.
A 1 3 3 -
B 2 3 4 -
C 4 5 6 A
D 8 9 10 B
E 2 5 8 C, D
F 4 5 6 D
G 1 2 3 E
i) Draw an AON network for this project. (3marks)
ii) Determine the expected time and variance for each activity. (4marks)
iii) Find the probability that Mr Jame’s project will be finished in 16 weeks or less. (7marks)
b) Explain what is project crashing and outline the rules that are followed in doing the crashing. (6marks)
Question Five (20marks)
A factory makes the two types of components for the motor car industry. Two machines are required for the manufacturer of each component.
Component X requires 11/2 hour on machine 1 and 1 hour on machine 2.
Component Y requires 2 hours on machine 1 and 3 hours on machine 2. In a given period these are 2,400 hours available on both machines. In addition, the material required for component X is in short supply and only sufficient material for 1,200 units in the period is available.
5
If the profit contribution from component X is ksh.20 and component Y is ksh.30 determine the optimum production schedule and the contribution for the period using the simplex method. (20marks)