List the five distinct aspects which the Project Manager should consider when preparing a project communications plan.

      

List the five distinct aspects which the Project Manager should consider when preparing a project communications plan.

  

Answers


Lydia
i. Stakeholder communications requirements
ii. Information to be communicated, including format, content, and level of detail
iii. Who will receive the information and who will produce it
iv. Suggested methods or technologies for conveying the information
v. Frequency of communication
vi. Escalation procedures for resolving issues
vii. Revision procedures for updating the communications management plan

lydiajane74 answered the question on October 10, 2017 at 11:29


Next: Fill in the blanks in the sentences below with the correct verb.
Previous: Give two disadvantages of intensive system of farming.

View More Business Studies Questions and Answers | Return to Questions Index


Exams With Marking Schemes

Related Questions