Give four methods of transporting wet concrete to the required position.

      

Give four methods of transporting wet concrete to the required position.

  

Answers


gideon
i) Using wheelbarrows.
ii) Using dampers.
iii) Hoisting by a winch.
iv) Raising it by the user of stepped
gideon1 answered the question on October 11, 2017 at 06:59