Lack of historical data and prior knowledge of an information system makes it difficult to estimate the cost of an information systems project. Required:Formulate a checklist...

      

Lack of historical data and prior knowledge of an information system makes it difficult to estimate the cost of an information systems project.
Required:
Formulate a checklist that could assist an organization in identifying, quantifying and evaluating information systems costs.

  

Answers


gregory

?
Feasibility study: Preparation of gross estimates of developments, implementation and operation
costs for each probable alternative solution.
?
Development costs are one-time costs that will not recur after the project has been
completed e.g. systems development, hardware/software, user training, site preparation
and data conversion.
?
Operating costs are costs that tend to recur throughout the lifetime of the system. E.g.
maintenance, data storage expenses, communications expenses, software licenses. Such
costs can be classified as:
Fixed costs – occur at regular intervals but at relatively fixed rates
Variable costs – occur in proportion to some usage factor.
gregorymasila answered the question on November 27, 2017 at 13:24


Next:  What is meant by prototyping? Briefly comment on its advantages and disadvantages and explain how this approach is used.
Previous: The basic objective of user interface is to minimize the human error during data entry. Required (i) Explain the error control measures that should be incorporated into...

View More Computer Science Questions and Answers | Return to Questions Index


Learn High School English on YouTube

Related Questions