Explain the term 'critical path' as used in project management

      

Explain the term 'critical' path as used in project management.

  

Answers


gregory
Critical path
This is a term used in project scheduling in relation to network analysis diagrams (a general
term that includes techniques such as critical path analysis/critical path method (CPM), and
Project Evaluation and Review Technique (PERT) charts). In a network analysis diagram, the
critical path is defined as one with the following characteristics:
1.The earliest starting times (ESTs) and the latest starting times (LSTs) of all events along the
path are equal.
2.The sum of the activity durations of all activities along the path is greater than all other
parts.
3.All activities along the path have no float (amount of slack time associated with a non-
critical activity).
All activities along the critical path are critical since we cannot afford to take longer than the
time allocated without affecting the project completion time.
gregorymasila answered the question on November 29, 2017 at 09:00


Next: Describe the role of project management
Previous: Briefly describe any four computer related crimes that an organisation which is considering computerising its operations should be aware of

View More Computer Science Questions and Answers | Return to Questions Index


Exams With Marking Schemes

Related Questions