Annan agreed to paint Angela's house at an agreed price. When Annan had finished thework. Angela discovered that although most of the painting was satisfactory,...

      

Annan agreed to paint Angela's house at an agreed price. When Annan had finished thework. Angela discovered that although most of the painting was satisfactory, Annan had forgotten to apply a coat of gloss paint on one of the doors. Annan fell ill and could not complete the work. Angela refused to pay Annan the contractual price, claiming that the contract had not been fully executed and that therefore he was entitled to be paid only a reasonable sum for the work he had actually undertaken. This, Annan
claimed, was much less than the contract price.

Advise Annan.

  

Answers


Raphael
- This problem is based on the exceptions of the common law doctrine of precise and exact i.e. substantial performance.

- In this case it is clear that Annan has substantially performed his part of the contract and is
therefore entitled to payment for work done.

- Angela is bound to pay Annan the contract price less the amount she is likely to spend to have the door painted as agreed and since Angela has paid a “reasonable” sum for Annan's work, Annan has no cause of action against Angela. However if the amount is too low, he may have a cause of action for breach of contract.

- My advise to Annan is that he has no actionable claim against Angela. This advise is based
on the decision in Marshides Mehta and Co. Ltd. V Barron Verhegen whose facts were
substantially similar.
raphael answered the question on April 17, 2018 at 18:12


Next: Give ways in which arid lands can be made more productive
Previous: In relation to the Law of Property, state five obligations of a lessor towards a lessee in a lease agreement.

View More CPA Commercial Law Questions and Answers | Return to Questions Index


Learn High School English on YouTube

Related Questions