Explain with an appropriate example, how a materials requirement planning (MRP) system works.

      

Explain with an appropriate example, how a materials requirement planning (MRP) system works.

  

Answers


Lydia
• Master Production Schedule – includes forecast demand and actual orders
• Explosion of BOM – a detailed breakdown of all component parts within the final product
• Stock levels – quantity, location and transaction records
• Lead-times – time required from order to delivery including safety margin.