Get premium membership and access questions with answers, video lessons as well as revision papers.

Explain with an appropriate example, how a materials requirement planning (MRP) system works.

      

Explain with an appropriate example, how a materials requirement planning (MRP) system works.

  

Answers


Lydia
• Master Production Schedule – includes forecast demand and actual orders
• Explosion of BOM – a detailed breakdown of all component parts within the final product
• Stock levels – quantity, location and transaction records
• Lead-times – time required from order to delivery including safety margin.
lydiajane74 answered the question on July 1, 2018 at 09:36


Next: Using a product of your choice, examine the content and purpose of the design process.
Previous: Discuss the benefits and challenges associated with the implementation of an MRP system.

View More Business Studies Questions and Answers | Return to Questions Index


Learn High School English on YouTube

Related Questions