Sixteen men working at a rate of nine hours a day can complete a piece of work in 14 days. How many more men working...

      

Sixteen men working at a rate of nine hours a day can complete a piece of work in 14 days. How many more men working at a rate of 7 hours a day would complete the same job in 12 days?

  

Answers


martin
=(16×9×14)/(7×12)
=24
Answer will be 24-16=8
=8 men
matokibs answered the question on September 17, 2018 at 12:07