Explain the following terms used in network analysis: i) Network planning; ii) Activities; iii) Events; iv) Critical path; v) Float.

Explain the following terms used in network analysis:
i) Network planning;
ii) Activities;
iii) Events;
iv) Critical path;
v) Float.

Answers


Wilfred
i) Network planning is the arrangement of activities and events in a diagram to create a logical relationship from start to end making up a project.
ii) Activities are those actions that take up resources and time.
iii) Events indicate start or completion of activities
iv) Critical path is a combination of activities that, if any of them is delayed, then the projects duration will also delay. That is, they are critical to the projects duration. They are activities with zero floats.
v) Float is the amount of time an activity can be delayed without delaying the overall time of the project.
Wilfykil answered the question on February 20, 2019 at 07:18