Vick Press Ltd is planning to expanding into offering security systems in people?s homes scared of security.The following are activities and associated costs for the expansion:

      

Vick Press Ltd is planning to expanding into offering security systems in people‟s homes scared of security.The following are activities and associated costs for the expansion:
vic12022019136.png

Required:
i) Determine the critical path.
ii) Determine the minimum time and minimum cost for the networks.
iii) Given that, for every delay beyond 40th week, there is share of Sh.1,000 per week loss of profit. Is it advisable to crash the project from 51 to 45 weeks? Why?

  

Answers


Wilfred
vic22022019138.png
vic32022019138.png
Wilfykil answered the question on February 20, 2019 at 09:39


Next: Peter and Ngomongo are second hand dealers of electronic equipment and shoes along Baricho road. Due to hard economic times and restriction by City Council, sales...
Previous: Name four types of terrace constructed in a farm

View More CPA Quantitative Analysis Questions and Answers | Return to Questions Index


Learn High School English on YouTube

Related Questions