MMK Ltd. plans to conduct a survey. The following table shows the tasks involved, the immediately preceding tasks and for each activity duration the most...

      

MMK Ltd. plans to conduct a survey. The following table shows the tasks involved, the immediately preceding tasks and for each activity duration the most likely estimate (L), the optimistic estimate (O) and the pessimistic estimate (P).
mmk12022019257.png

Required:
a) Compute the mean duration and standard deviation for each task
b) The project is budgeted to cost Sh.500,000. Actual costs per day are Sh.10,000. By first identifying the critical path from drawing a network diagram can the project be implemented within the budget.
c) What is the probability of finishing the project 4 days earlier than the expected duration?

  

Answers


Wilfred
mmk22022019305.png
Wilfykil answered the question on February 20, 2019 at 11:05


Next: Discuss strategies of rural development
Previous: How does differential calculus assist managers in their optimization problems when faced with single variables?

View More CPA Quantitative Analysis Questions and Answers | Return to Questions Index


Exams With Marking Schemes

Related Questions