In relation to project analysis define the terms: i) Latest start time. ii) Earliest start time. iii) Resource leveling.

      

In relation to project analysis define the terms:
i) Latest start time.
ii) Earliest start time.
iii) Resource leveling.

  

Answers


Wilfred
i) Latest start time is the last time that an activity can start and be completed on time without delaying subsequent activities.
ii) Earliest start time is the first time an activity can start immediately after the preceding activity
iii) Is the shifting of non-critical activities between earliest and latest starting times to reduce the maximum number of resource required assuming that units of resources are perfect substitutes
Wilfykil answered the question on February 20, 2019 at 12:25


Next: A milk processing plant Oldonyo Kesses Ltd in Rift-Valley desires to determine how many kilograms of butter to produce per day to meet demand. Past...
Previous: A project has 11 activities with the activities preceding constraints, time estimates and work team requirements as shown

View More CPA Quantitative Analysis Questions and Answers | Return to Questions Index


Exams With Marking Schemes

Related Questions