A project has 11 activities with the activities preceding constraints, time estimates and work team requirements as shown

      

A project has 11 activities with the activities preceding constraints, time estimates and work team requirements as shown
est12022019426.png

Required:
i) Prepare a network and indicate critical path.
ii) Prepare a time chart and work team requirement.
iii) Can the work team resource be levelled further? Why?

  

Answers


Wilfred
est22022019429.png
est32022019429.png
Wilfykil answered the question on February 20, 2019 at 12:30


Next: In relation to project analysis define the terms: i) Latest start time. ii) Earliest start time. iii) Resource leveling.
Previous: State three methods of presentation during public speaking