Contractors began to trade on 1st April, 2004.

      

Contractors began to trade on 1st April, 2004.
The following was the expenditure on the contract for Kshs. 300,000. Materials issued to contract Kshs.
51,000, plant used for contract Kshs. 15,000, wages incurred Kshs. 81,000. Other expenses incurred Kshs.
5,000 cash received on account to 31st March, 2005, amounted to 128,000 being 80% of the work certified.
Of the plant and materials charged to the contract, plant which cost Kshs. 3,000 and materials which cost Kshs. 2,500 were lost. On 31st March, 2005 plant which cost Kshs. 2,000 was returned to store, the cost of work done but uncertified was Kshs. 1,000 and materials costing Kshs. 2,300 were in hand on site. Charge 15% depreciation on plant.

Prepare the contract account and the contractee’s account from the above particulars.

  

Answers


Wilfred
cont31642019850.png
Wilfykil answered the question on April 16, 2019 at 05:51


Next: What are the problems of Orientation?
Previous: Greed is dehumanizing. Using the Pearl for illustrations support the truth of the statement.

View More Cost Accounting Questions and Answers | Return to Questions Index


Learn High School English on YouTube

Related Questions