Construction Ltd. is engaged on two contracts A and B during the year. The following particulars are obtained at the end of the year (Dec....

      

Construction Ltd. is engaged on two contracts A and B during the year. The following particulars are obtained at the end of the year (Dec. 31)
const11642019913.png

During the period materials amounted to Kshs. 9,000 have been transferred from contract A to contract B.
You are required to show.
(a) Contract account
(b) Contractees accounts
(c) Extract from balance sheet as at Dec. 31.

  

Answers


Wilfred
const1b1642019914.png
const1c1642019915.png
Wilfykil answered the question on April 16, 2019 at 06:16