- The vast land of 14721 acres is divided into plots of 1Ha.
- Each plot is surrounded by ridges of earth to hold water.
- A main canal is constructed to direct water from the Rivers Thiba/Nyamidi.
- From the main canal, smaller canals are dug to access the plots/farms.
- Water flows into the main canal then to the smaller canals/plots of land by gravity.
- The plots of land get flooded in readiness for paddy rice cultivation.
- Fertilizers application takes place to upscale soil drainage and fertility.
Kavungya answered the question on May 30, 2019 at 09:29


Next: The diagram below shows a rectangular wire with loose thread tied in it and dipped in a soap solution to form a film. Draw a diagram...
Previous: A uniform rod of length 4m and mass of 4kg is pivoted at 3.6m mark. The rod is held horizontal with a vertical rope at...

View More Geography Questions and Answers | Return to Questions Index


Exams With Marking Schemes

Related Questions