Six men can complete a job in 20 days. If the men Work at the same rate, how many more are needed to complete the...

      

Six men can complete a job in 20 days. If the men Work at the same rate, how many more are needed to complete the job in 12 days?

A. 16
B. 10
C. 8
D. 4

  

Answers


Wilfred
The correct answer is [D]

1562839845788-201617.png
1562839939801-201618.png
The key word is how many more men.
= 10 – 6
= 4 men
Wilfykil answered the question on July 30, 2019 at 05:37