An organization intends to replace an existing system by carrying out the process in stages. (a) Name this implementation strategy. (b) Give two reasons why the organization

      

An organization intends to replace an existing system by carrying out the process in stages.
(a) Name this implementation strategy.
(b) Give two reasons why the organization is opting to use the implementation strategy above.

  

Answers


gideon
(a) Phased implementation (1mk)
(b) (i) It causes minimal disruption to the operation of the organisation.
(ii) Employees will be trained prior to the fully implementation of the system.
(iii) The organisation will not require additional personnel.
(iv) Risk of system failures will be minimal.
(v) The strategy is less costly.
gideon1 answered the question on September 29, 2017 at 08:56


Next: State four input/output devices found at the electronic point of sale.
Previous: A computer is idle but the hard disk light is blinking, indicating some activity. State two possible causes of this.

View More Computer Studies Questions and Answers | Return to Questions Index