What is a priority rule?

      

What is a priority rule?

  

Answers


Ruth
A priority rule contains information to construct a list of activities that ranks all project activities a certain order to determine the priority in which the activities are assigned to the project schedule. Such a list is constructed based on the project data in order to assign priorities to activities as follows:
1. Activity information
Information about time or cost estimates of the activities determines the activities.
2. Network Information
Information obtained from simple critical path scheduling tools determines the activity priorities.
3. Resource Information
Information about projects resources determines the activity priority.

NatalieR answered the question on June 13, 2022 at 06:16


Next: Highlight the challenges that cause continuous update of schedules
Previous: Enumerate the approaches used for loading work centers

View More Production and Operation Management Questions and Answers | Return to Questions Index


Learn High School English on YouTube

Related Questions