i. Finish-to-start-The beginning of a task is dependent on the completion of all its predecessors.
ii. Finish-to-finish-The completion of a task is dependent on the completion of all Its predecessors.
iii. Start-to-start-The start of a task is dependent on the start of all Its predecessors.
iv. Start-to-finish-The completion of a task is dependent on the start of all its predecessors.
francis1897 answered the question on March 13, 2023 at 13:48
- State the two techniques of activity sequencing(Solved)
State the two techniques of activity sequencing
Date posted: March 13, 2023. Answers (1)
- What are the benefits that arise from proper scheduling?(Solved)
What are the benefits that arise from proper scheduling?
Date posted: March 13, 2023. Answers (1)
- How can you develop a project schedule?(Solved)
How can you develop a project schedule?
Date posted: March 13, 2023. Answers (1)
- What is activity sequencing?(Solved)
What is activity sequencing?
Date posted: March 13, 2023. Answers (1)
- State the activity characteristics(Solved)
State the activity characteristics
Date posted: March 13, 2023. Answers (1)
- Briefly describe project time management processes(Solved)
Briefly describe project time management processes
Date posted: March 13, 2023. Answers (1)
- State some of the time robbers(Solved)
State some of the time robbers
Date posted: March 13, 2023. Answers (1)
- Define the term time robbers(Solved)
Define the term time robbers
Date posted: March 13, 2023. Answers (1)
- What are the elements of the staffing management plan?(Solved)
What are the elements of the staffing management plan?
Date posted: March 13, 2023. Answers (1)
- Describe the project organizational chart(Solved)
Describe the project organizational chart
Date posted: March 13, 2023. Answers (1)
- Give the benefits and drawbacks of the roles and responsibilities matrix(Solved)
Give the benefits and drawbacks of the roles and responsibilities matrix
Date posted: March 13, 2023. Answers (1)
- Describe the roles and responsibilities matrix (RRM) as a human resource management key deliverable(Solved)
Describe the roles and responsibilities matrix (RRM) as a human resource management key deliverable
Date posted: March 13, 2023. Answers (1)
- State and explain the five interpersonal influence types managers may have(Solved)
State and explain the five interpersonal influence types managers may have
Date posted: March 13, 2023. Answers (1)
- State the ways project managers can receive project authority(Solved)
State the ways project managers can receive project authority
Date posted: March 13, 2023. Answers (1)
- What are the best opportunity and worst opportunity for success?(Solved)
What are the best opportunity and worst opportunity for success?
Date posted: March 13, 2023. Answers (1)
- What are the types of Authority Influence?(Solved)
What are the types of Authority Influence?
Date posted: March 13, 2023. Answers (1)
- Authority is defined as either legal or acquired. Explain(Solved)
Authority is defined as either legal or acquired. Explain
Date posted: March 13, 2023. Answers (1)
- State human resource management best practices(Solved)
State human resource management best practices
Date posted: March 13, 2023. Answers (1)
- Give a summary of the Herzberg’s Research(Solved)
Give a summary of the Herzberg’s Research
Date posted: March 13, 2023. Answers (1)
- Describe the Herzberg view on staff motivation(Solved)
Describe the Herzberg view on staff motivation
Date posted: March 13, 2023. Answers (1)