Get premium membership and access questions with answers, video lessons as well as revision papers.

Describe the precedence diagramming method (PDM)

      

Describe the precedence diagramming method (PDM)

  

Answers


Francis
- Uses boxes to represent activities (nodes) and lines with arrows to represent the dependencies.

Capture 2.JPG

- The task names are for this example shortened to just letters. The lines with arrows are not labeled
- Notice that some of the activities (C, F, G, and H) have more than one predecessor; some only have a successor (Begin) and some only have a predecessor (End).
- The PDM illustrates four types of dependencies between activities.
francis1897 answered the question on March 13, 2023 at 13:55


Next: Describe the process of creating a sample activity-on-arrow (AOA) network diagram
Previous: What important issues should you consider in estimating resources?

View More Management of IT Projects Questions and Answers | Return to Questions Index


Learn High School English on YouTube

Related Questions