State some of the activity resources process deliverables

      

State some of the activity resources process deliverables

  

Answers


Francis
(i). Activity resource requirements- a list of activity resource requirements for each activity within all the work packages, a
project resource organization chart and WBS, a hierarchical breakdown of resources by category and type.

(ii). Resource calendars - showing the availability of each resource (detailing vacation,holidays,and days available to work
on the project)

(iii). Assigned resources (resource loading) - lists the amount of each resource that the project schedule requires during
specific timeperiods.
- Project managers can use loading to make sure that resources are not over utilized; for instance, project
management software will notify you that you have someone working 24 hours a day, but it will allow you to do it.
francis1897 answered the question on March 14, 2023 at 05:26


Next: What are the techniques for resource estimating?
Previous: Describe the typical problems with estimates

View More Management of IT Projects Questions and Answers | Return to Questions Index


Learn High School English on YouTube

Related Questions