Describe the typical problems with estimates

      

Describe the typical problems with estimates

  

Answers


Francis
1. Developing an estimate for a large technology project is a complex task requiring a significant amount of effort.

2. estimates are done at various stages of the project “Progressive Elaboration”
- ROM (-25% to + 75%) or SWAG
- Budget (-10% to + 25%)
- Definitive (-5% to 10%)

3. Many people doing estimates have little experience doing them.

4. People have a bias toward underestimation. Review estimates and ask important questions to make sure estimates are not biased

5. Management wants a number for a bid or just to look good to superiors, not a real estimate. Project managers must
negotiate with project sponsors to create realistic estimates
francis1897 answered the question on March 14, 2023 at 05:43


Next: State some of the activity resources process deliverables
Previous: What are the activity duration estimation methods?

View More Management of IT Projects Questions and Answers | Return to Questions Index


Exams With Marking Schemes

Related Questions