Organic:
Effort = 2.4 x KLOC1.05 where KLOC = 1000 lines of code
Duration = 2.5 x Effort 0.38
Semidetached
Effort = 3.0 x KLOC1.12
Duration = 2.5 x Effort 0.35
Embedded
Effort = 3.6 x KLOC1.2
Duration = 2.5 x Effort 0.32
francis1897 answered the question on March 14, 2023 at 06:31
- Describe the techniques for estimating time(Solved)
Describe the techniques for estimating time
Date posted: March 14, 2023. Answers (1)
- What are the issues with function points?(Solved)
What are the issues with function points?
Date posted: March 14, 2023. Answers (1)
- State the advantages with function points(Solved)
State the advantages with function points
Date posted: March 14, 2023. Answers (1)
- What are the uses for function points?(Solved)
What are the uses for function points?
Date posted: March 14, 2023. Answers (1)
- Describe the process of function points(Solved)
Describe the process of function points
Date posted: March 14, 2023. Answers (1)
- Function point analysis is based on an evaluation of five data and transactional types that define the application boundary. By the use of a diagram,...(Solved)
Function point analysis is based on an evaluation of five data and transactional types that define the application boundary. By the use of a diagram, describe this statement.
Date posted: March 14, 2023. Answers (1)
- What are the advantages and disadvantages of the lines of code(LOC)?(Solved)
What are the advantages and disadvantages of the lines of code(LOC)?
Date posted: March 14, 2023. Answers (1)
- Describe the task sizing methods(Solved)
Describe the task sizing methods
Date posted: March 14, 2023. Answers (1)
- What are the activity duration estimation methods?(Solved)
What are the activity duration estimation methods?
Date posted: March 14, 2023. Answers (1)
- Describe the typical problems with estimates(Solved)
Describe the typical problems with estimates
Date posted: March 14, 2023. Answers (1)
- State some of the activity resources process deliverables(Solved)
State some of the activity resources process deliverables
Date posted: March 14, 2023. Answers (1)
- What are the techniques for resource estimating?(Solved)
What are the techniques for resource estimating?
Date posted: March 14, 2023. Answers (1)
- What important issues should you consider in estimating resources?(Solved)
What important issues should you consider in estimating resources?
Date posted: March 14, 2023. Answers (1)
- Describe the precedence diagramming method (PDM)(Solved)
Describe the precedence diagramming method (PDM)
Date posted: March 13, 2023. Answers (1)
- Describe the process of creating a sample activity-on-arrow (AOA) network diagram(Solved)
Describe the process of creating a sample activity-on-arrow (AOA) network diagram
Date posted: March 13, 2023. Answers (1)
- Describe the Arrow Diagramming Method (ADM) of activity sequencing(Solved)
Describe the Arrow Diagramming Method (ADM) of activity sequencing
Date posted: March 13, 2023. Answers (1)
- State the activity dependency types(Solved)
State the activity dependency types
Date posted: March 13, 2023. Answers (1)
- State the two techniques of activity sequencing(Solved)
State the two techniques of activity sequencing
Date posted: March 13, 2023. Answers (1)
- What are the benefits that arise from proper scheduling?(Solved)
What are the benefits that arise from proper scheduling?
Date posted: March 13, 2023. Answers (1)
- How can you develop a project schedule?(Solved)
How can you develop a project schedule?
Date posted: March 13, 2023. Answers (1)