Describe the critical chain scheduling as a tool used for schedule development

      

Describe the critical chain scheduling as a tool used for schedule development

  

Answers


Francis
- Technique that addresses the challenge of meeting or beating project finish dates and an application of the Theory of Constraints (time, resources, cost, scope, etc.), one aspect that limits a project’s ability to achieve more of its goals, weakest links
- Developed by Eliyahu Goldratt in his book The Goal
- Critical chain is a method of scheduling that takes constraints into account when creating a project schedule and includes buffers to protect the project completion date unlike CPM which is only based on time
francis1897 answered the question on March 14, 2023 at 07:47


Next: State the importance of updating critical path data
Previous: Describe the resource loading and leveling as a tool used for schedule development

View More Management of IT Projects Questions and Answers | Return to Questions Index


Exams With Marking Schemes

Related Questions