- Resource loading defines the amount of time a specific resource is needed over each time period
- Project software is great at highlighting issues of overloading a resource – having a resource working more time in a day than is available.
- Resource leveling: Is the process of rescheduling activities on the project schedule that have available slack to achieve a more balanced distribution of resource usage
- Project software will do this for you…within limits!