Get premium membership and access questions with answers, video lessons as well as revision papers.

Describe the resource loading and leveling as a tool used for schedule development

      

Describe the resource loading and leveling as a tool used for schedule development

  

Answers


Francis
- Resource loading defines the amount of time a specific resource is needed over each time period
- Project software is great at highlighting issues of overloading a resource – having a resource working more time in a day than is available.
- Resource leveling: Is the process of rescheduling activities on the project schedule that have available slack to achieve a more balanced distribution of resource usage
- Project software will do this for you…within limits!
francis1897 answered the question on March 14, 2023 at 07:51


Next: Describe the critical chain scheduling as a tool used for schedule development
Previous: What are the resource leveling activities?

View More Management of IT Projects Questions and Answers | Return to Questions Index


Learn High School English on YouTube

Related Questions