- Resource loading defines the amount of time a specific resource is needed over each time period
- Project software is great at highlighting issues of overloading a resource – having a resource working more time in a day than is available.
- Resource leveling: Is the process of rescheduling activities on the project schedule that have available slack to achieve a more balanced distribution of resource usage
- Project software will do this for you…within limits!
francis1897 answered the question on March 14, 2023 at 07:51
- Describe the critical chain scheduling as a tool used for schedule development(Solved)
Describe the critical chain scheduling as a tool used for schedule development
Date posted: March 14, 2023. Answers (1)
- State the importance of updating critical path data(Solved)
State the importance of updating critical path data
Date posted: March 14, 2023. Answers (1)
- State some of the techniques used for shortening a project schedule (Schedule Analysis)(Solved)
State some of the techniques used for shortening a project schedule (Schedule Analysis)
Date posted: March 14, 2023. Answers (1)
- Define the methods used to find the critical path(Solved)
Define the methods used to find the critical path
Date posted: March 14, 2023. Answers (1)
- Describe the Critical Path Method (CPM) as a tool used for schedule development.(Solved)
Describe the Critical Path Method (CPM) as a tool used for schedule development.
Date posted: March 14, 2023. Answers (1)
- Describe Program Evaluation and Review Technique (PERT) as a tool used for schedule development(Solved)
Describe Program Evaluation and Review Technique (PERT) as a tool used for schedule development
Date posted: March 14, 2023. Answers (1)
- What are the benefits of schedule development?(Solved)
What are the benefits of schedule development?
Date posted: March 14, 2023. Answers (1)
- What are the issues that arise with COCOMO?(Solved)
What are the issues that arise with COCOMO?
Date posted: March 14, 2023. Answers (1)
- State the advantages of COCOMO(Solved)
State the advantages of COCOMO
Date posted: March 14, 2023. Answers (1)
- What are the COCOMO levels?(Solved)
What are the COCOMO levels?
Date posted: March 14, 2023. Answers (1)
- Describe effort sizing(Solved)
Describe effort sizing
Date posted: March 14, 2023. Answers (1)
- Describe the techniques for estimating time(Solved)
Describe the techniques for estimating time
Date posted: March 14, 2023. Answers (1)
- What are the issues with function points?(Solved)
What are the issues with function points?
Date posted: March 14, 2023. Answers (1)
- State the advantages with function points(Solved)
State the advantages with function points
Date posted: March 14, 2023. Answers (1)
- What are the uses for function points?(Solved)
What are the uses for function points?
Date posted: March 14, 2023. Answers (1)
- Describe the process of function points(Solved)
Describe the process of function points
Date posted: March 14, 2023. Answers (1)
- Function point analysis is based on an evaluation of five data and transactional types that define the application boundary. By the use of a diagram,...(Solved)
Function point analysis is based on an evaluation of five data and transactional types that define the application boundary. By the use of a diagram, describe this statement.
Date posted: March 14, 2023. Answers (1)
- What are the advantages and disadvantages of the lines of code(LOC)?(Solved)
What are the advantages and disadvantages of the lines of code(LOC)?
Date posted: March 14, 2023. Answers (1)
- Describe the task sizing methods(Solved)
Describe the task sizing methods
Date posted: March 14, 2023. Answers (1)
- What are the activity duration estimation methods?(Solved)
What are the activity duration estimation methods?
Date posted: March 14, 2023. Answers (1)