Get premium membership and access questions with answers, video lessons as well as revision papers.

What are the resource leveling activities?

      

What are the resource leveling activities?

  

Answers


Francis
(i). Move activities – manually move activities by changing the discretionary dependencies or entering hard dates
(ii). Split – manually split activities such that only part of the activity is done at one time
(iii). Reduce resource availability – change the resource so they are not working full time on the task which will have the effect of lengthening the activity duration
(iv). Change/add resources to the task
(v). Authorizing the resource to work overtime
francis1897 answered the question on March 14, 2023 at 07:53


Next: Describe the resource loading and leveling as a tool used for schedule development
Previous: How can you level benefits?

View More Management of IT Projects Questions and Answers | Return to Questions Index


Learn High School English on YouTube

Related Questions