What are the resource leveling activities?

      

What are the resource leveling activities?

  

Answers


Francis
(i). Move activities – manually move activities by changing the discretionary dependencies or entering hard dates
(ii). Split – manually split activities such that only part of the activity is done at one time
(iii). Reduce resource availability – change the resource so they are not working full time on the task which will have the effect of lengthening the activity duration
(iv). Change/add resources to the task
(v). Authorizing the resource to work overtime
francis1897 answered the question on March 14, 2023 at 07:53