Describe the mitigation strategies for risk

      

Describe the mitigation strategies for risk

  

Answers


Francis
- The final step after the risk response has been chosen; update the risk register with the mitigation strategy: fallback
plans, contingency plans, and contingency reserves.
Fallback plans
Contingency plans.
Contingency reserves
- Contingency plans use the contingency reserves to meet project objectives
francis1897 answered the question on March 14, 2023 at 11:28