It takes 30 workers 6 days working at the rate of 8 hours a day to harvest maize in a farm. How many days would 50 workers working 6 hours a day take to harvest the maize?.

Class: Form 1

Subject: Mathematics

Topic: Rates, Ratios, Proportions and Percentages

Lesson Summary

It takes 30 workers 6 days working at the rate of 8 hours a day to harvest maize in a farm. How many days would 50 workers working 6 hours a day take to harvest the maize?.



Text Answer


q4942019338.png

50 x 6 x y = 1440
Y =1440𝟓𝟎𝒙𝟔= 4.8 days.